Construction of External and Internal Electrical Networks for Chkalov Agro LLC

Connection of the Biogas Power Plant of Chkalov Agro LLC with a Total Capacity of 6004 kW

Completed all design, installation, and connection works to the electrical grid for the I&U Group Agroholding. The 6 MW/h biogas complex will process sugar production waste into raw materials for thermal and electrical energy, and after commissioning, it will annually produce 48,180 MWh of "green" electricity.

Image

Construction of External and Internal Electrical Networks for Chkalov Agro LLC

Connection of the Biogas Power Plant of Chkalov Agro LLC with a Total Capacity of 6004 kW

Completed all design, installation, and connection works to the electrical grid for the I&U Group Agroholding. The 6 MW/h biogas complex will process sugar production waste into raw materials for thermal and electrical energy, and after commissioning, it will annually produce 48,180 MWh of "green" electricity.

Image
Image
Image
Image
Image
Image
Image
Image

Construction of External and Internal Electrical Networks for Chkalov Agro LLC

Connection of the Biogas Power Plant of Chkalov Agro LLC with a Total Capacity of 6004 kW

Completed all design, installation, and connection works to the electrical grid for the I&U Group Agroholding. The 6 MW/h biogas complex will process sugar production waste into raw materials for thermal and electrical energy, and after commissioning, it will annually produce 48,180 MWh of "green" electricity.

Image

The facility has been commissioned.

Completed Works

During 2019-2020, our organization carried out a full range of works to provide external and internal power supply for the biogas complex, specifically:

Reliable Partnership

Feedback on Our Work

Completed all design, installation, and connection works to the electrical grid for the I&U Group Agroholding.

Image
Image

completed projects

Like What You See? Get More Information!

Facility Details:

  • Facility Address: Territory of Kapitanivska Village Council, Novomyrhorod District, Kirovohrad Region
  • Total Capacity: 6004 kW
  • Line Voltage: 110 kV, Category III reliability of power supply
  • Metering System: AMR (Automated Meter Reading)
  • Type of Power Line: PL-110 kV with AS-240/32 conductor
  • Equipment Type: TMN-6300/110/10, 10/0.4 kV Transformer Substation
  • Implementation Timeline: 12 months