In the period from December 2017 to March 2018, our company performed a full range of works to ensure the external power supply of the Yuriy-Pharm production, namely:
The design and estimate documentation for the installation of additional 10kV cells in RU-10kV networks of PJSC "Cherkasioblenergo", the laying of 10kV cable lines, the construction of ZTP-10/0.4kV and the implementation of the ACEMS system was developed and agreed with the operator of the distribution system of PJSC "Cherkasioblenergo".
At the connection points, two 10kV cells are installed in the networks of PJSC "Cherkasioblenergo".
The ZTP-10/0.4kV Yuryia-Farm building with 2x1000kVa transformers was built, and its grounding was completed.
Two 10 kV cable lines were laid to ZTP-10/0.4 kV, with a puncture through the street. Hetman Sahaidachny and along the street Narbutivska The length of the track is 1200 m.
In RU-10kV and RU-0.4kV of the new ZTP-10/0.4kV substations are installed and busbared.
Accounting was organized on the 0.4kV side and the ACEMS system was implemented.
Full legal support was provided and a contract was signed for the distribution of electricity to the consumer with PJSC "Cherkasioblenergo".
Commissioning works have been completed, the facility has been put into operation.