During the project implementation, our team completed a full range of works on the installation and automation of a solar power plant to replace its own needs, namely
Developed design and estimate documentation for the installation of the solar power plant.
All equipment and structures were purchased and delivered to the site.
Automation to limit overgeneration was installed.
Installed on the roof of the SPP warehouse, 2 HUAWEI SUN2000-50KTL-M3 inverters were installed in the 0.4kV switchgear.
Metal structures and photovoltaic modules of the SPP with a capacity of 97 kW were installed.
All electrical installation and commissioning works have been completed
The SPP facility of YURIA-PHARM LLC was put into operation.