In the period from May to July 2020, our company completed a full range of works to ensure external power supply to the confectionery production, namely:
- Design and estimate documentation for the reconstruction of 10 kV cells in the 10 kV switchgear of 110/10 kV Magnit SS and the implementation of the AMR system was developed and agreed with the distribution system operators of PJSC Cherkasyoblenergo.
- Two 10 kV cells were reconstructed in the 10 kV switchgear of 110/10 kV Magnit SS.
- Metering on the 10 kV side was organized and the AMR system was implemented.
- Full legal support was provided and an electricity distribution agreement was signed with PJSC Cherkasyoblenergo.
- Commissioning works were completed and the facility was put into operation.