In the period from November 2019 to February 2020, our company performed a full range of works to ensure the external and internal power supply of the solar station, namely:
- Design and estimate documentation for the construction of the SPP, reconstruction of PJSC "Cherkasioblenergo" networks, construction of a 10kV cable line from the 110/10kV Magnet substation to the customer's networks, KTP-10/0.4kV, ACEMS, RZA and telemechanics systems was developed.
- The installation and adjustment of the 10 kV cell in the 110/10 kV Magnet substation with RZA, telemechanics and ACEMS systems was completed.
- Cable lines of 10 kV were laid from PS 110/10 kV Magnet to KTP-10/0.4 kV with a total length of 1 km.
- KTP-10/0.4kV LLC "LIFE ENERGY" with RZA, telemechanics and ACEMS systems was installed and adjusted.
- Full legal support was provided, contracts were signed for the distribution of electricity between the consumer and the producer with PJSC "Cherkasioblenergo".
- A license and a green tariff were obtained for "LIFE ENERGY" LLC, and the necessary contracts were concluded with PJSC "NEK" Ukrenergo" and SE "Guaranteed Buyer" for the transmission and sale of electric energy.
- The FES of "LIFE ENERGY" LLC with an installed capacity of 624.96 kW was built.
- Commissioning works have been completed, the SES facility of "LIFE ENERGY" LLC has been put into operation.